Enhanced Commissioning

LEED 2.2 Requirements:

Implement, or have a contract in place to implement, the following additional commissioning process activities in addition to the requirements of EA Prerequisite 1 and in accordance with the LEED-NC 2.2 Reference Guide:

  1. Prior to the start of the construction documents phase, designate an independent Commissioning Authority (CxA) to lead, review, and oversee the completion of all commissioning process activities. The CxA shall, at a minimum, perform Tasks 2, 3 and 6. Other team members may perform Tasks 4 and 5.
    • The CxA shall have documented commissioning authority experience in at least two building projects.
    • The individual serving as the CxA shall be— a.independent of the work of design and construction; b.not an employee of the design firm, though they may be contracted through them; c.not an employee of, or contracted through, a contractor or construction manager holding construction contracts; and d.(can be) a qualified employee or consultant of the Owner.
    • The CxA shall report results, findings and recommendations directly to the Owner.
    • This requirement has no deviation for project size.
  2. The CxA shall conduct, at a minimum, one commissioning design review of the Owner’s Project Requirements (OPR), Basis of Design (BOD), and design documents prior to mid-construction documents phase and back-check the review comments following design submission.
  3. The CxA shall review contractor submittals applicable to systems being commissioned for compliance with the OPR and BOD. This review shall be concurrent with A/E reviews and submitted to the design team and the Owner.
  4. Develop a systems manual that provides future operating staff the information needed to understand and optimally operate the commissioned systems.
  5. Verify that the requirements for training operating personnel and building occupants are completed.
  6. Assure the involvement by the CxA in reviewing building operation within 10 months after substantial completion with O&M staff and occupants. Include a plan for resolution of outstanding commissioning-related issues.

Submittals (CONSTRUCTION):

- Provide the name and company for the CxA.
- Indicated that the CxA meets the qualifications outlined in the credit requirements.
- Confirm that the 6 required tasks have been completed.
- Provide a narrative describing the enhanced commissioning processes that were employed on the project (include a description of the results of the commissioning design review, implementation of the systems manual and training, and the plan for the review of building operation at 8 to 10 months). AND (For Projects With Special Circumstances)
- Provide an optional narrative to describe any additional comments or notes regarding special circumstances or considerations regarding the project's credit approach.

ENERGY AND ATMOSPHERE
EA PR1 Fundamental Commissioning of the Building Energy Systems
EA PR2 Minimum Energy Performance
EA PR3 Fundamental Refrigerant Management
EA 1 Optimize Energy Performance
EA 2 On-Site Renewable Energy
EA 3 Enhanced Commissioning
EA 4 Enhanced Refrigerant Management
EA 5 Measurement and Verification
EA 6 Green Power
 
 
The Vision and Mission of the Central Texas - Balcones Chapter
Vision: Buildings and communities will regenerate and sustain the health and vitality of all life.
Mission: Accelerate the transformation toward sustainable building and land development practices in Central and South Texas through innovation, education, advocacy and partnerships.
USGBC CENTRAL TEXAS - BALCONES
Copyright © Central Texas - Balcones Chapter U.S. Green Building Council. All Rights Reserved
USGBC