Fundamental Commissioning of the Building Energy Systems
LEED 2.2 Requirements:
The following commissioning process activities shall be completed by the commissioning team, in accordance with the LEED-NC 2.2 Reference Guide.
- Designate an individual as the Commissioning Authority (CxA) to lead, review and oversee the completion of the commissioning process activities.
- The CxA shall have documented commissioning authority experience in at least two building projects.
- The individual serving as the CxA shall be independent of the project’s design and construction teams, though they may be employees of the firms providing those services. The CxA may be a qualified employee or consultant of the Owner.
- The CxA shall report results, findings and recommendations directly to the Owner.
- For projects smaller than 50,000 gross square feet, the CxA may include qualified persons on the design or construction teams who have the required experience.
- The Owner shall document the Owner’s Project Requirements (OPR). The design team shall develop the Basis of Design (BOD). The CxA shall review these documents for clarity and completeness. The Owner and design team shall be responsible for updates to their respective documents.
- Develop and incorporate commissioning requirements into the construction documents.
- Develop and implement a commissioning plan.
- Verify the installation and performance of the systems to be commissioned.
- Complete a summary commissioning report.
Commissioned Systems Commissioning process activities shall be completed for the following energy-related systems, at a minimum:
- Heating, ventilating, air conditioning, and refrigeration (HVAC&R) systems (mechanical and passive) and associated controls
- Lighting and daylighting controls
- Domestic hot water systems
- Renewable energy systems (wind, solar etc.)
Submittals (CONSTRUCTION):
- Provide the name and company information for the CxA.
- Confirm that the 6 required tasks have been completed.
- Provide a narrative description of the systems that were commissioned and the results of the commissioning process. AND (For Projects With Special Circumstances)
- Provide an optional narrative to describe any additional comments or notes regarding special circumstances or considerations regarding the project's prerequisite approach. |