Water Efficient Landscaping: No Potable Water Use or No Irrigation
LEED 2.2 Requirements:
Achieve WE Credit 1.1. and: Use only captured rainwater, recycled wastewater, recycled graywater, or water treated and conveyed by a public agency specifically for non-potable uses for irrigation.
OR
Install landscaping that does not require permanent irrigation systems. Temporary irrigation systems used for plant establishment are allowed only if removed within one year of installation.
Option 3:
The landscaping and irrigation systems have been designed to reduce irrigation water consumption from a calculated baseline case, AND the irrigation water used on site is supplied by a non-potable source (up to 2 points).
Option 4:
The landscaping installed does not require permanent irrigation systems. Temporary irrigation systems used for plant establishment will be removed within one year of installation. (2 points).
Submittals (DESIGN):
- Provide the project landscape plan(s).
- Provide a narrative describing the landscaping and irrigation design strategies employed by the project; description of the water use calculation methodology used to determine savings; and for projects using non-potable water, specific information regarding source and available quantity of non-potable supplies. In addition, please provide the following project data and calculation information based on the appropriate compliance path:
Option 3
- Landscaping and Irrigations Systems Design AND Non-Potable Irrigation Water Source
- Provide the project's calculated baseline irrigation water consumption (Total Water Applied (TWA) (gal)). This data an be obtained using Equation 5 (p. 121 of LEED Reference Manual).
- Provide the project's calculated design case irrigation water consumption (Total Water Applied (TWA) (gal)). This data can be obtained by using Equation 5.
- Provide the total non-potable water supply (gal) available for irrigation purposes.
- Provide the non-potable water source.
Option 4
- No Permanent Irrigation System
- There are no additional items required for this compliance path. AND (For Projects With Special Circumstances
- Any Compliance Path)
- Provide an optional narrative to describe any additional comments or notes regarding special circumstances or considerations regarding the project's credit approach. |